The Help to Buy scheme will end on 31 May 2021 and the stamp duty holiday on 30 June 2021. The next few months will be a busy time for completions to meet these deadlines. Don’t worry, Premier Guarantee is here to help.
In order that we can support you to meet these deadlines, please take note of the following points:
Talk through your forecasted completions with your risk management surveyor. Use the Premier Guarantee Extranet to make sure any outstanding information shown on your technical overview is up to date: find them attached to each site inspection report.
Ensure any drainage tests are made ready if they are to be carried out at the same time as the pre-handover inspection.
When booking a final inspection, give as much notice as possible to your risk management surveyor. Please remember we need at least 24 hours’ notice.
Ensure the plot is ready at the time of inspection and will pass the UK Finance Logic Test.
On or before the time of inspection make sure all your commissioning certificates are ready and available.
The plot should be presented in line with Standard Operational Procedures and Risk and Method Statements to ensure compliance with Covid requirements.
Download an action plan flyer to add to your noticeboard.
Please note: deadlines referenced are applicable to England only.